VDOT Apron, Concrete Driveway, and Retaining Walls Alexandria, VA

A VDOT apron, a new concrete driveway and brick retaining walls in Alexandria, VA, with stone work on the stoop, Mexican beach pebble stone and sod, all done front to back by Tuck GC including the VDOT permitting.

VDOT Apron, Concrete Driveway, and Retaining Walls Alexandria, VA (video)

Filmed on site by Tuck. Watch on YouTube or see all project videos.

Project at a glance

City / CountyAlexandria, VA (Fairfax County)
JurisdictionVDOT Land Use Permit on a state-maintained street
ScopeVDOT apron; concrete driveway; brick retaining walls; stone work on the front stoop; Mexican beach pebble stone; sod
Materials & brandsPoured concrete; brick; natural stone on the stoop; Mexican beach pebble; sod
VideoVideo published February 2019

About this project

This Alexandria, VA project ran front to back: a VDOT apron at the street, a new concrete driveway, brick retaining walls, stone work on the front stoop, Mexican beach pebble stone, and sod. The homeowner had no driveway at all. We built a new one from scratch, with new retaining walls and the grading needed to flatten the yard.

Who permitted the apron

Inside the independent City of Alexandria, a driveway apron or curb cut is permitted by the city's Department of Transportation & Environmental Services (T&ES), not by VDOT. On a state-maintained street in Fairfax County the apron sits in VDOT right-of-way and needs a VDOT land use permit with a refundable surety. This entrance was built as a VDOT apron. In our experience these reviews commonly take one to two months, and the disturbed ground around the new apron has to be restored and stabilized with established grass before VDOT signs off and releases the surety.

How we build this scope

A standard residential driveway is typically 4 inches thick. A VDOT apron built to the CG-9D spec used in Fairfax and Prince William must be a minimum of 7 inches thick. We install VDOT #21A crushed stone to the depth the entrance standard and permit require, compacted in lifts, and we reinforce an apron only where the jurisdiction's detail calls for it. Our standard 4-inch driveway gets about 8 inches of excavation and about 4 inches of compacted #21A crushed stone, with 6x6 welded wire mesh pulled up into the center of the slab during the pour and a slip-resistant broom finish.

Behind a retaining wall we place drainage stone and a drainage pipe as specified in your proposal, giving groundwater an exit path instead of letting hydrostatic pressure stack up behind the structure. In most Northern Virginia jurisdictions, a retaining wall that retains more than three feet of soil requires a local building permit and inspection.